Re: How to run a Program Performance report during specific time period?

Dan_Stevens_
Level 10 - Champion Alumni

How to run a Program Performance report during specific time period?

When running the Program Performance report within "Analytics", we need a way to view this data by time period (e.g., a specific quarter).  When I click on the "Report" tab to view the results, there is a filter icon followed by "All Time".  Clicking on this should allow me to define a specific timeframe.  But all it does is take me to the "Setup" tab - where there is no option to define a specific timeframe.  How can this be accomplished?
12 REPLIES 12
Anonymous
Not applicable

Re: How to run a Program Performance report during specific time period?

Expand the "Settings" dropdown, and you can change the value of "Date of Activity". From there you can choose a set of times, or use a custom date.

Hope this helps,
JayF
Dan_Stevens_
Level 10 - Champion Alumni

Re: How to run a Program Performance report during specific time period?

There is no SETTINGS drop-down.  Just to clarify, the Program Performance report includes ALL programs - which is what we require here.  Basically, show us the performance of all programs for a defined time period.

0EM50000000R1r6.jpg

Anonymous
Not applicable

Re: How to run a Program Performance report during specific time period?

Go to your set up tab and you can choose the specified time there.
Dan_Stevens_
Level 10 - Champion Alumni

Re: How to run a Program Performance report during specific time period?

I did that - but there is no place to define a specific timeframe there. 
Michelle_Tizian
Level 10

Re: How to run a Program Performance report during specific time period?

Dan is correct.  You can't change the time frame.  I just tried doing this myself.  When I tried to change the time frame from the default of all time, it automatically takes me to the set up tab, but there's nothing in that area that will allow me to change the time frame.  
Anonymous
Not applicable

Re: How to run a Program Performance report during specific time period?

hmmm, you're right. I was looking at the wrong report. This seems like a funny bug...
Jacqui_Murphy
Level 2

Re: How to run a Program Performance report during specific time period?

This is still a bug... I would love to filter by day/week but this is also not possible.
Anonymous
Not applicable

Re: How to run a Program Performance report during specific time period?

Hi, is there a resolution to this issue?

Thanks.

Rick_Sysol1
Level 1

Re: How to run a Program Performance report during specific time period?

Bumping this one again.

Are there any plans to add the ability to adjust timeframe per quarter, month, year, etc. for this report?